Carmel College
Location: St HelensValue: £1,000,000
Main Contractor: Kier North West
Commenced: October 2008
Scope of Works:
The project comprises of SFS, Aluminium cladding panels, insulated render and perforated air flow panelling. The contract was secured in 2008 and is to run in two phases with phase 1 completed by the end of May 2009 followed by phase 2 in 2010.
MIB Façades UK Ltd has worked closely with Kier North West to deliver a façade encompassing design and the installation of all materials.
Duration:
Phase 1, 26 weeks
Phase 2, 15 weeks