Carmel College

Location: St Helens
Value: £1,000,000
Main Contractor: Kier North West
Commenced: October 2008

 

  • Carmel College image 1
  • Carmel College image 2
  • Carmel College image 3
  • Carmel College image 4
  • Carmel College image 5
  • Carmel College image 6

 

Scope of Works:
The project comprises of SFS, Aluminium cladding panels, insulated render and perforated air flow panelling. The contract was secured in 2008 and is to run in two phases with phase 1 completed by the end of May 2009 followed by phase 2 in 2010.

 

MIB Façades UK Ltd has worked closely with Kier North West to deliver a façade encompassing design and the installation of all materials.

 

Duration:

Phase 1, 26 weeks
Phase 2, 15 weeks

 

*
*